AQW 15816/17-22 Written question to the Minister for Communities

To ask the Minister for Communities, pursuant to AQW 14955/17-22, to detail the steps taken by her Department to (i) reduce the number of (a) applicants; and (b) applicants in housing stress in East Londonderry; and (ii) increase the number of allocations to applicants.

Asked by Claire Sugden MLA on 4 March 2021

  • Answered
  • Written
Tabled
4 March 2021
Answer due by
22 March 2021
Answered
18 March 202114 days after tabling
Department
Department for Communities
Priority question
No

Answer

I have set out an ambitious and long-term plan to increase the supply of social and also affordable housing and to reduce housing stress. My plan includes:

Changing the status of the landlord part of the Housing Executive so that it can borrow, invest in its homes and ultimately start building again;

Bringing forward a consultation on the future of the Housing Executive House Sales Scheme, as soon as practicably possible in order to protect the current supply of social housing;

Reintroducing ring-fencing of the new build Social Housing Development Programme (SHDP) to prioritise areas of highest housing need.

Introducing reform of the social housing allocations system;

Ensuring the Housing Executive prioritises adaptations;

Developing new ways to help people into home ownership and continuing to support shared ownership schemes, such as, Co-Ownership;

Expanding the rental options available by introducing intermediate rent to provide an additional supply of good quality, well managed and maintained homes, which are affordable for lower income families;

Working proactively to prioritise actions to improve our response to homelessness with a continued focus on prevention rather than management; and

Developing a Housing Supply Strategy to provide a framework for addressing those whole system issues that impact on housing supply and the delivery of the right volume and types of homes to meet our changing housing need and demand.

In the shorter term the key action taken to reduce the numbers of Housing Applicants, including those in Housing Stress; and to increase the number of allocations, is to deliver new social housing through the Social Housing Development Programme.

In the East Derry Parliamentary constituency there have been 52 new social housing units completed to-date in 2020/21. These units are detailed in Table 1 below.

Table 1: Social housing completions to-date in 2020/21 in East Derry Parliamentary Constituency

Housing AssociationScheme NameLocationTypeNeed GroupStrategic GroupUnitsOnsite Year
ChoiceBeresford AvenueColeraineNew BuildGeneral NeedsUrban142019/20
Clanmil13 Union StreetColeraineNew BuildActive ElderlyUrban182017/18
Habinteg45 Girona AvenuePortrushNew BuildGeneral NeedsUrban72018/19
Habinteg45 Girona AvenuePortrushNew BuildWheelchairUrban32018/19
RuralSite adjacent to 299 Foreglen RoadForeglenNew BuildGeneral NeedsRural32019/20
Triangle21 ParkleaPortstewartExisting Satisfactory PurchaseGeneral NeedsUrban12016/17
Triangle22 AshdaleColeraineExisting Satisfactory PurchaseGeneral NeedsUrban12016/17
Triangle8-10 Upper Captain StreetColeraineExisting Satisfactory PurchaseGeneral NeedsUrban52016/17

A further 132 new social housing units are under construction. These units are detailed in Table 2 below.

Table 2: Social housing units under construction in East Derry Parliamentary Constituency

Housing AssociationScheme NameLocationTypeNeed GroupStrategic GroupUnitsOnsite YearCompletionYear
Apex HousingHass Road Phase 3 (T)DungivenNew BuildGeneral NeedsRural182020/212021/22
Apex HousingHass Road Phase 3 (T)DungivenNew BuildWheelchairRural42020/212021/22
Apex HousingHass Road Phase 3A (T)DungivenNew BuildWheelchairRural12020/212021/22
ArkRailway RoadColeraineOff-the-ShelfGeneral NeedsUrban122020/212021/22
ChoiceThe Hill, PortstewartPortstewartNew BuildGeneral NeedsUrban92020/212022/23
Radius(Site adjacent to 191) Coleraine RoadPortstewartNew BuildGeneral NeedsUrban572019/202021/22
Radius(Site adjacent to 191) Coleraine RoadPortstewartNew BuildActive ElderlyUrban122019/202021/22
Radius(Site adjacent to 191) Coleraine RoadPortstewartNew BuildWheelchairUrban62019/202021/22
TrianglePortstewart RoadColeraineOff-the-ShelfGeneral NeedsUrban62019/202020/21
TriangleHarpurs Hill, Phase 2 (T)ColeraineNew BuildGeneral NeedsUrban42020/212021/22
TriangleHarpurs Hill, Phase 2 (T)ColeraineNew BuildWheelchairUrban32020/212021/22
Housing AssociationScheme NameLocationTypeNeed GroupStrategic GroupUnitsOnsite YearCompletionYear
Apex HousingHass Road Phase 3 (T)DungivenNew BuildGeneral NeedsRural182020/212021/22
Apex HousingHass Road Phase 3 (T)DungivenNew BuildWheelchairRural42020/212021/22
Apex HousingHass Road Phase 3A (T)DungivenNew BuildWheelchairRural12020/212021/22
ArkRailway RoadColeraineOff-the-ShelfGeneral NeedsUrban122020/212021/22
ChoiceThe Hill, PortstewartPortstewartNew BuildGeneral NeedsUrban92020/212022/23
Radius(Site adjacent to 191) Coleraine RoadPortstewartNew BuildGeneral NeedsUrban572019/202021/22
Radius(Site adjacent to 191) Coleraine RoadPortstewartNew BuildActive ElderlyUrban122019/202021/22
Radius(Site adjacent to 191) Coleraine RoadPortstewartNew BuildWheelchairUrban62019/202021/22
TrianglePortstewart RoadColeraineOff-the-ShelfGeneral NeedsUrban62019/202020/21
TriangleHarpurs Hill, Phase 2 (T)ColeraineNew BuildGeneral NeedsUrban42020/212021/22
TriangleHarpurs Hill, Phase 2 (T)ColeraineNew BuildWheelchairUrban32020/212021/22

A total of 95 units are currently programmed to start as part of the Social Housing Development Programme (SHDP) 2020/21 – 2022/23. These units are detailed in Table 3 below.

Table 3: Social housing units programmed to start 2020/21 – 2022/23 in East Derry Parliamentary Constituency

Housing AssociationScheme NameLocationTypeNeed GroupStrategic GroupUnitsOnsite YearCompletionYear
ChoiceKeely Gardens (T)AghadoweyNew BuildGeneral NeedsRural42020/212021/22
Apex HousingCoastguard RoadColeraineNew BuildGeneral NeedsRural62021/222022/23
ChoiceCaptain StreetColeraineNew BuildGeneral NeedsUrban312021/222023/24
ChoiceCaptain StreetColeraineNew BuildWheelchairUrban42021/222023/24
ChoiceBeresford AvenueColeraineNew BuildGeneral NeedsUrban502022/232024/25

Official sources