AQW 30499/17-22 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure, pursuant to AQW 29917/17-22, (i) for her assessment of the current capability of Ballykelly’s wastewater system; and (ii) to detail any remaining issues that have been identified with the system.
Asked by Claire Sugden MLA on 3 March 2022
- Answered
- Written
- Tabled
- 3 March 2022
- Answer due by
- 21 March 2022
- Answered
- 11 March 20228 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
(i)NI Water completed a £5 million upgrade to Ballykelly’s wastewater treatment works in October 2021. The works, which incorporate a solar energy system and integrated constructed wetlands, is a long-term, sustainable and resilient solution. It is now fully operational and has a design Population Equivalent (PE) of 5000.
(ii)There are currently no remaining issues in the system and I would add that a significant stormwater project (c. £900k) was also completed approximately 3 years ago, which addressed a flooding issue affecting Hyacinth Avenue. This stormwater project also reduced flows to the works.