AQW 31115/17-22 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure pursuant to AQW 30742/17-22, whether wastewater infrastructure provision in Limavady is also of a standard to support the construction of future developments.

Asked by Claire Sugden MLA on 22 March 2022

  • Answered
  • Written
Tabled
22 March 2022
Answer due by
25 March 2022
Answered
24 March 20222 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

NI Water has advised that there are three investment schemes proposed for the Limavady area in Price Control 21 (2021-2027), subject to funding. These are Bovally wastewater pumping station (£1.35m), Limavady catchment upgrades (£2.133m) and Ballyclose Street Combined Sewer Overflow (£1.256m) and once they have been completed successfully, this should address most, if not all, of the existing catchment constraints.

According to NI Water’s analysis, conducted in July 2021, NI Water has advised that the headroom capacity of the Limavady wastewater treatment works would permit the connection of approximately 1200 domestic properties, taking into account an allowance for non-domestic development.