AQW 10994/22-27 Written question to the Minister of Justice

To ask the Minister of Justice, pursuant to AQW 31197/17-22, (i) when the outline business case for HMP Magilligan was submitted; (ii) to provide details on the outcome of this, including actions that will result and the associated timeframe; and (iii) whether funding is available and in place for the planned work.

Asked by Claire Sugden MLA on 29 April 2024

  • Answered
  • Written
  • Priority
Tabled
29 April 2024
Answer due by
2 May 2024
Answered
2 May 20243 days after tabling
Department
Department of Justice
Priority question
Yes

Answer

Approval for the associated expenditure in the Outline Business Case 1 (OBC) for the Redevelopment of Magilligan Prison Project was granted by Department of Finance (DoF) in May 2022.

However, due to significant cost inflation, NIPS has determined that this work should proceed on a phased approach, determined by urgent business need, commencing with the preparation of OBC1s for a New Kitchen and Café and an additional wing at Halward House. Funding requirements for these projects will be informed by the OBC1s which are being progressed.

Funding allocations will be determined by budget availability. All contractual commitments will have to be prioritised before other projects can be funded.

Official sources