AQW 40768/22-27 Written question to the Minister for Infrastructure
To ask the Minister for Infrastructure to detail the £3.8 million estimated cost of the proposed park and ride facility at Bellarena railway halt, including a breakdown of costs for (i) design; (ii) land acquisition; (iii) construction; and (iv) associated works.
Asked by Claire Sugden MLA on 17 February 2026
- Answered
- Written
- Tabled
- 17 February 2026
- Answer due by
- 4 March 2026
- Answered
- 4 March 202615 days after tabling
- Department
- Department for Infrastructure
- Priority question
- No
Answer
The table below provides a breakdown of estimated costs to deliver the new Park and Ride facility at Bellarena Rail Halt.
| Item | Cost |
| Construction | £2,794,701 |
| Project management, design and statutory fees | £259,419 |
| Optimum Basis and sunk costs | £547,836 |
| Inflation | £221,924 |
| Total | £3,823,880 |