AQW 9590/22-27 Written question to the Minister of Agriculture, Environment and Rural Affairs

To ask the Minister of Agriculture, Environment and Rural Affairs for an explanation of the delay of the Northern Ireland Environment Agency in responding to planning applications as a statutory consultee.

Asked by Claire Sugden MLA on 8 April 2024

  • Answered
  • Written
Tabled
8 April 2024
Answer due by
23 April 2024
Answered
17 April 20249 days after tabling
Department
Department of Agriculture, Environment and Rural Affairs
Priority question
No

Answer

The primary reason for NIEA delay in responding to planning applications is that the number of complex planning consultations receipted exceeds the capacity that staff in post have to respond. Contributing factors include the number of re-consultations received / the quality of information submitted, and the level of non-statutory work associated with the delivery of our planning role and responsibilities.